GSD-UEN-GAR-2026-04280 & GSD-UEN-GAR-2026-04310

Great News: ASADA de Lomas del Mar Is Now Technically Feasible!


This milestone follows years of work to resolve significant legal, technical and infrastructure challenges. 

Key steps included:

  • Completing the loop work, which provided a temporary way to carry out infrastructure improvements while easements were being registered
  • Segregating and donating Tanks 2 and 5 and the well to the ASADA, and legally registering the properties and easements for water use
  • Completing the 72-hour stress test and water-quality testing
  • Obtaining the Ministry of Health operating certificate for the well
  • Securing the water concession after resolving the discovery that the well identified as CN-613 was actually CN-476—a discrepancy that created major delays and regulatory obstacles
  • Painting the tanks AyA blue and installing perimeter fencing

Please give a warm thank you to not only the Board of Directors, but also all of the employees who were instrumental in our success.